Timing
Start planning when peaks consistently exceed 60–70% of capacity. Upgrades involve new optics and possibly new cross-connects, so leave time.
Parallel build
Ask for the new port to be provisioned alongside the existing one. Install optics and patch the new cross-connect.
Move services step by step
- Bring up new route server sessions on the new port.
- Shift bilateral peering sessions.
- Move private VLANs and virtual circuits.
- Confirm traffic is flowing on the new port.
Verify
After each step, check BGP sessions, routes and traffic graphs. Keep the old port available to roll back.
Decommission
Once everything is stable on the new port, shut the old one and arrange its removal.